Signaling works, telecommunications and energy
Mitre Line – Bancalari, Escobar, Campana, and Zárate stations

The signaling system with relay interlocking is being implemented, which is vital for the implementation of ATS (Automatic Train Stop). The work includes civil works, track renewal, and replacement of track switches.

Mitre Line (Retiro – J. L. Suárez Branch) section between Empalme Maldonado and Pueyrredon station

Implementation of the signaling system with electronic interlocking.

Belgrano Sur Line – between stations Tapiales and Marinos del Crucero General Belgrano

• Progress is being made on the signaling system with relay interlocking, which is vital for the implementation of ATS.

• Implementation of a telecommunications system via a fiber optic network.

Sarmiento Line, Haedo-Moreno Section

• New audio frequency track circuits (AFC) and a new cable network for the existing signaling system

• Renewal of the trunk cables between stations.

San Martín Line Connection Section

Work is underway to install a signaling system with relay interlocking, vital for the implementation of the ATS (Automatic Train Services). The work includes civil and track works for the connection of both lines at Mercedes station.

Merlo-Lobos Branch

The implementation of a signaling system is being carried out through the installation of relay interlocking, vital in the Merlo, M. Acosta, M. Paz, Las Heras, Hornos, Empalme Lobos, and Lobos sections.

The works include the installation of radio links for interlocking communication, the installation of the ATS system, civil works for the new technical rooms, and the renewal of track switches.

Moreno – Mercedes Branch Line

The implementation of a signaling system is underway, through the installation of a relay interlocking system, vital in the Moreno, General Rodríguez, Luján, and Mercedes areas.
The works include the installation of radio links for interlocking communication, the installation of the ATS system, civil works for the new technical rooms, and the renewal of track switches.